| Novartis CMF and PDU
Facility Upgrades
Emeryville, California
Major modifications to Novartis’s manufacturing
facilities must be constructed and validated within their annual shutdown
period. Completing complex projects within a limited time frame requires
close coordination throughout the design effort, pre-ordering of major
components and equipment and early installation of systems not located
within the GMP controlled areas. VDK was part of a design/build team selected
by Novartis to implement a series of compliance upgrades for the Clinical
Manufacturing Facility (CMF) and the Process Development Unit (PDU) at
the Novartis Emeryville Campus.
The work in the CMF included construction of a new multi-product
formulations laboratory and renovation of the locker/gowning/toilet room
core to provide flexibility for production processes and enhanced cGMP
compliance.
The PDU improvements included construction of a new
inoculum preparation laboratory to serve the production unit and the installation
of new pass-through equipment to improve the flow of glassware between
the fermentation suite and the glass washroom. |